by Kate Shunney
An interstate project to connect a natural gas pipeline from Southern Fulton, Pa. to northern Morgan County has work continuing at multiple sites, including horizontal directional drilling under the Potomac River.
A biweekly status report on the 3.4-mile natural gas extension project says that contractors for the pipeline project have made a stream crossing with the 8-inch pipeline, are drilling at the Potomac River crossing and began drilling activities along I-68 during…